Most of the underground piping that makes the new Visitor & Administration Building's water, sewer, and recycled water systems function has been completed.  Framing of the underside of the Terrace Canopy has begun.  Work continues on  the Auditorium's architectural concrete walls.

Inside the building, painting and door installation has begun, and work on the elevator is underway.

Top right: Section of the architectural concrete Auditorium wall under the Terrace Canopy.

Bottom right: Primed interior of the Administrative Offices