| Work inside the main building continues as the equipment for the geothermal system is installed and ceilings are put into place. Outside, the piping and foundations of the rainwater, graywater and geothermal systems are being excavated and installed.
A mockup for the architectural concrete walls of the Auditorium has been poured, and work will begin on the real walls soon. These walls feature board-formed poured concrete that will have the natural texture of wood.
Top right: Bird's eye view of the foundation of the Cleansing Biotope being poured
Bottom right: Architectural concrete wall sample
Photographs by Max Joel
<<next entry| previous entry>> |