Queens Botanical Garden - Where people, plants, and cultures meet

The steel frame of the Visitor/Administration Building has been assembled and concrete floor and ceiling planks are being put into place. The foundation for the Auditorium has been poured, and in October its walls will rise above grade.

The Horticulture/Maintenance Building is nearing completion. Queens Botanical Garden staff will move into their new offices and workspaces in October.

Top right: Steel frame of the Visitor/Administration Building

Bottom right: Completed garage bay in the Horticulture/Maintenance Building

Photographs by Max Joel

<<next entry| previous entry>> 

 

 
 


Copyright 2006 Queens Botanical Garden | 43-50 Main Street, Flushing, NY 11355