Queens Botanical Garden - Where people, plants, and cultures meet

The foundation and concrete basement walls of the Visitor & Administration Building have been poured, and the 24,000 gallon cistern that will store rainwater to supply the water feature has been installed. In September, the building's structural steel will begin to rise above ground.

The Horticulture/Maintenance Building is nearing completion. Queens Botanical Garden staff will move into their new offices and workspaces in September.

Top right: Rainwater cistern section is lowered into place by crane.

Bottom right: View of the Visitor & Administration Building foundation with Auditorium excavation and current Administration Building in background.

Photographs by Max Joel

<<next entry| previous entry>>

 
 


Copyright 2006 Queens Botanical Garden | 43-50 Main Street, Flushing, NY 11355